Resurfacing works at the crossroads in Treuddyn.

road ahead closedResurfacing works at the crossroads in Treuddyn.

This has been causing a huge problem for residents who are having to divert along the Sarn past Plas ym Mhowys and Plas y Brain as it’s so narrow.

Carolyn has spoken with the Technical Officer who said the crossroads needed to be done as the area was unlikely to last another harsh Winter.

They couldn’t do one section at at time or let vehicles pass with the HGV vehicles working because of road width regulations, safety, etc.

He also said if traffic starts using the road before it is set, once the new surface goes on then it will cause more issues.

They are making this section a priority each morning before doing the other section that is damaged by the Sunspot.

** LATEST UPDATE ** 17.00 Monday 14th July

The contractors have been let down regarding delivery of tarmac from the quarry which won’t be there now until Wednesday. 

The new plan is to get the crossroads open with traffic management tomorrow while the work cannot take place, the tarmac will then be laid Wednesday with a closure in place between 9.00 am and 4.00 pm and Thursday while the surface dressing is being added between 9.00 am and 4.00 pm. 

Hopefully, it will be reopen and finished Friday.