Update on Gas Supply in Treuddyn

gasWe have an update from Rachel Webber about the gas supply to the village.
Dear Resident,

As you may be aware Wales and West Utilities are progressing well and the link in Leeswood was completed on October 1st.
The next stage in the process involves preliminary works for the governor site, which should be completed over the next 7 days.
Following on from this, the works will then begin on Ffordd Top Y Rhos, eventually linking to the preliminary works on Ffordd Y Llan over the coming weeks.

In the meantime, our heating contractors Warmer Energy are in the process of conducting surveys for private residents requiring a central heating installation. Once this has been completed Flintshire County Council will then issue the quotations.

Thank you to those who have provided us with the evidence required for the Gas Connection Voucher. The team was in Treuddyn on Friday 9th October and this was an opportunity for any remaining applicants wishing to access the voucher, to provide us with the relevant documents required. If you wish to make an appointment please contact either Rachael or Hayley on the telephone number below.

Hayley Cummins – 01352 703443 – Project Support Officer
Rachael Webber – 01352 703425 – Project Support Assistant

Regards
Rachael Webber
Housing Regeneration & Strategy
Community and Enterprise Portfolio
Flintshire County Council

cadwyn-clwydflintshire-partnershipwag

Site design and development: Colony of Ants

This web site is proudly powered by WordPress